66 tasks, day 1 to 80 80
Architectural designDay 1 to 15, 15 work days
Construction documentsDay 16 to 30, 15 work days, starts after Architectural design
Permit review and approvalDay 31 to 60, 30 work days, starts after Construction documents
Permit review and approval
Budget finalization and procurementDay 31 to 50, 20 work days, starts after Construction documents
Budget finalization and procurement
Finish selectionsDay 61 to 80, 20 work days, starts after Permit review and approval and Budget finalization and procurement
Site mobilizationDay 61 to 65, 5 work days, starts after Permit review and approval and Budget finalization and procurement
1414 tasks, day 66 to 123 58
Erosion controlDay 66 to 68, 3 work days, starts after Site mobilization
Site clearing and gradingDay 69 to 73, 5 work days, starts after Erosion control
Site clearing and grading
ExcavationDay 74 to 78, 5 work days, starts after Site clearing and grading
Footing forms and rebarDay 79 to 83, 5 work days, starts after Excavation
Footing pourDay 84 to 85, 2 work days, starts after Footing forms and rebar and Permit review and approval
Footing cureDay 88 to 92, 5 work days, starts after Footing pour
Foundation wallsDay 93 to 97, 5 work days, starts after Footing cure
Foundation waterproofingDay 98 to 100, 3 work days, starts after Foundation walls
Foundation drain tileDay 101 to 102, 2 work days, starts after Foundation waterproofing
Backfill and rough gradeDay 105 to 108, 4 work days, starts after Foundation drain tile
Underslab plumbingDay 109 to 111, 3 work days, starts after Backfill and rough grade
Slab preparation and reinforcingDay 112 to 114, 3 work days, starts after Underslab plumbing
Slab preparation and reinforcing Slab pourDay 115 to 116, 2 work days, starts after Slab preparation and reinforcing
Slab cureDay 119 to 123, 5 work days, starts after Slab pour
55 tasks, day 124 to 152 29
First-floor framingDay 124 to 131, 8 work days, starts after Slab cure
Second-floor framingDay 132 to 138, 7 work days, starts after First-floor framing
Roof framingDay 139 to 144, 6 work days, starts after Second-floor framing
Roof sheathingDay 145 to 149, 5 work days, starts after Roof framing
Framing inspectionDay 151 to 152, 2 work days, starts after Roof sheathing and Roof framing
66 tasks, day 150 to 170 21
RoofingDay 150 to 154, 5 work days, starts after Roof sheathing
Window installationDay 150 to 154, 5 work days, starts after Roof sheathing
Exterior doorsDay 155 to 157, 3 work days, starts after Window installation
Housewrap and flashingDay 150 to 153, 4 work days, starts after Roof sheathing
Siding installationDay 154 to 165, 12 work days, starts after Housewrap and flashing
Exterior trimDay 166 to 170, 5 work days, starts after Siding installation
55 tasks, day 158 to 174 17
Rough plumbingDay 158 to 167, 10 work days, starts after Exterior doors
Rough electricalDay 158 to 167, 10 work days, starts after Exterior doors
Rough HVACDay 158 to 169, 12 work days, starts after Exterior doors
Low-voltage wiringDay 168 to 172, 5 work days, starts after Rough electrical
Rough MEP inspectionDay 172 to 174, 3 work days, starts after Rough HVAC and Rough plumbing and Rough electrical
1313 tasks, day 175 to 251 77
InsulationDay 175 to 179, 5 work days, starts after Rough MEP inspection and Low-voltage wiring
Drywall hangingDay 180 to 187, 8 work days, starts after Insulation
Drywall finishingDay 188 to 197, 10 work days, starts after Drywall hanging
Prime paintDay 198 to 201, 4 work days, starts after Drywall finishing
Interior doors and trimDay 202 to 211, 10 work days, starts after Prime paint
Cabinet installationDay 212 to 219, 8 work days, starts after Interior doors and trim
Tile installationDay 220 to 231, 12 work days, starts after Cabinet installation
Flooring installationDay 232 to 239, 8 work days, starts after Tile installation
Countertop installationDay 227 to 231, 5 work days, starts after Cabinet installation and Tile installation
Interior paintDay 240 to 246, 7 work days, starts after Flooring installation
Plumbing trimDay 247 to 251, 5 work days, starts after Interior paint
Electrical trimDay 247 to 251, 5 work days, starts after Interior paint
Appliance installationDay 232 to 234, 3 work days, starts after Countertop installation
44 tasks, day 134 to 178 45
Exterior paintDay 171 to 177, 7 work days, starts after Exterior trim
Driveway and flatworkDay 134 to 139, 6 work days, starts after Slab cure
LandscapingDay 150 to 156, 7 work days, starts after Driveway and flatwork
Deck and porchDay 171 to 178, 8 work days, starts after Exterior trim
55 tasks, day 252 to 266 15
Final cleaningDay 252 to 254, 3 work days, starts after Plumbing trim and Electrical trim and Appliance installation
Punch list completionDay 255 to 259, 5 work days, starts after Final cleaning
Final inspectionDay 262 to 264, 3 work days, starts after Punch list completion
Owner orientationDay 265 to 265, 1 work day, starts after Final inspection
Project handoverDay 266 to 266, 1 work day, starts after Owner orientation