·Project Manager·Framing crew finished the second-floor walls this morning. We are holding the stair opening and north window checks before the afternoon inspection.
Use @ to mention teammates, and # to reference files, schedules, or selection items
Framing crew finished the second-floor walls this morning. We are holding the stair opening and north window checks before the afternoon inspection.
Owner approved the quartz selection for the kitchen island and perimeter counters. Please keep the eased edge detail from the showroom sample.
Budget scan found the rough plumbing invoice within allowance. The fixture package remains pending against the client selection list.
Uploaded 6 photos from today's walkthrough. Mechanical chases are marked, and blocking is ready for cabinet layout review.
Electrical rough-in walkthrough is ready for review. We flagged the pantry outlet height and moved the media conduit to align with the built-in elevation.