BuilderPadSettings
Approved
3

+$8,750

Pending
2

+$5,200

Rejected
1

Voided
1

Net to Contract
+$8,750

Approved total

Change order type
New change order
CO#
Title
Cost Code
Reason
Cost Delta
Schedule Delta
Submitted
Status
Type
001Foundation depth increase03-100Unforeseen condition+$3,750+5 daysMar 28, 2025APPROVEDINTERNAL
002Upgrade to engineered LVL beams06-100Client request+$2,4000 daysApr 18, 2025APPROVEDINTERNAL
003Add powder room finishes09-300Client request+$2,6000 daysApr 28, 2025APPROVEDOWNER
004Quartz upgrade in master12-300Selection overage+$1,2400 daysMay 1, 2025PENDINGOWNER
005Add deck framing scope06-100Client request+$3,960+7 daysMay 3, 2025PENDINGINTERNAL
006Skylight in master bath07-200Client request+$1,850+2 daysApr 12, 2025REJECTEDOWNER
007Custom built-ins in study06-200Client request+$5,400+5 daysDRAFTINTERNAL
008Site grading adjustment02-200Field condition+$0+1 dayApr 5, 2025VOIDEDINTERNAL