006Skylight in master bath07-200Client request+$1,850+2 daysApr 12, 2026OWNEROut-of-ScopeDRAW—REJECTED
010Rear elevation window upsize06-10006-200Client request+$4,200+3 daysMar 4, 2026OWNERMixedDRAW—APPROVED
011Upgrade kitchen island electrical16-100Client request+$5,5500 daysApr 9, 2026OWNEROut-of-ScopeDRAW—APPROVED
012Structural beam at kitchen opening06-100Unforeseen condition+$8,650+5 daysMay 14, 2026OWNEROut-of-ScopeDRAW—APPROVED
013Delete rear patio pergola06-200Descoped by owner-$2,400-2 daysJun 2, 2026OWNEROut-of-ScopeDRAW—APPROVED
014Master bath tile upgrade09-300Selection overage+$9,800+2 daysJun 18, 2026OWNEROut-of-ScopeDRAW—APPROVED
015Add conditioned crawlspace encapsulation07-200Inspector recommendation+$12,800+6 daysJul 7, 2026OWNEROut-of-ScopeDRAW—APPROVED
017Exterior lighting package16-100Client request+$3,2000 daysSep 2, 2026OWNEROut-of-ScopeDRAW—APPROVED
018Wine fridge and cabinet infill11-400Client paying direct, outside the draw+$6,4000 daysJun 24, 2026OWNEROut-of-ScopeDIRECT—APPROVED
005Add deck framing scopeUnder owner CO-00606-100Client request+$3,960+7 daysMay 3, 2026VENDOROut-of-Scope—PENDING
007Custom built-ins in studyUnder owner CO-00606-200Client request+$5,400+5 days—VENDOROut-of-Scope—DRAFT
008Site grading adjustmentUnder owner CO-00602-200Field condition$0+1 dayApr 5, 2026VENDORIn-Scope—VOIDED