Pipeline value
$203,611
Requested Jul 1, 2026, 10:00 AMDue Jul 10, 2026, 5:00 PM
Estimate
No line on this request is recorded as coming from this estimate.
Budget target
$42,000
From budget line 12-300
Internal — subs never see this
Spec snapshot
Scope lines
Harbor Cabinetry
SubmittedEmailNora BeckEstimatorestimating@harborcabinetry.example
Viewed Jul 1, 2026, 2:30 PMHarbor Cabinetry - Reed RFQ.pdfInvite link
Pricing assumes final field dimensions after drywall; standard maple veneer lead time is 8–10 weeks from approved shop drawings.
$68,400
As quoted
No quote
As quoted
No quote
As quoted
Leveled comparison carries scope gaps and exclusions; contract amount is payable scope.
| Vendor | Leveled comparison | vs budget target | Contract amount | As quoted | Status | Leveling notes |
|---|---|---|---|---|---|---|
1 Harbor Cabinetry Harbor Cabinetry - Reed RFQ.pdf | $69,250 | $27,250 over 65% | $69,250 | $68,400 | Complete | Include second field measure after drywall |