Total Cost
$1,300,525
Filtered transactions
Every posted job cost transaction grouped by inBuild cost code and vendor
| 01/08/2026 | 013100 Project management | Senior PM weekly allocation | BuilderPad Internal | $8,450 |
| 01/12/2026 | 015000 Temporary facilities | Site office setup and utilities | SiteReady Services | $14,875 |
| 01/17/2026 | 024100 Selective demolition | Interior demo phase 1 | Northline Demo | $42,600 |
| 01/24/2026 | 031000 Concrete forming | Foundation formwork materials | Cascade Lumber Supply | $23,940 |
| 01/31/2026 | 033000 Cast-in-place concrete | Foundation pour labor | Evergreen Concrete | $96,250 |
| 02/06/2026 | 033000 Cast-in-place concrete | Pump truck rental | Peak Equipment Rentals | $7,860 |
| 02/14/2026 | 042000 Unit masonry | Retaining wall masonry package | Stonegate Masonry | $58,400 |
| 02/22/2026 | 051200 Structural steel | Steel beam delivery | Western Steel Supply | $74,125 |
| 03/02/2026 | 051200 Structural steel | Crane and rigging | Summit Crane | $18,920 |
| 03/09/2026 | 061000 Rough carpentry | Framing crew draw 1 | FrameWorks NW | $132,500 |
| 03/16/2026 | 061000 Rough carpentry | Engineered lumber package | Cascade Lumber Supply | $86,700 |
| 03/22/2026 | 064000 Architectural woodwork | Cabinet shop deposit | Atelier Millworks | $52,800 |
| 03/28/2026 | 075000 Membrane roofing | Roofing mobilization | Rainline Roofing | $44,350 |
| 04/03/2026 | 079200 Joint sealants | Waterproofing sealant materials | Pacific Building Supply | $9,780 |
| 04/10/2026 | 081000 Doors and hardware | Exterior door package | Northwest Openings | $31,460 |
| 04/16/2026 | 092900 Gypsum board | Drywall labor progress billing | Precision Interiors | $88,900 |
| 04/21/2026 | 092900 Gypsum board | Level-five finish premium | Precision Interiors | $24,650 |
| 04/27/2026 | 096500 Resilient flooring | Flooring material order | Sound Surface Co. | $45,230 |
| 05/02/2026 | 099000 Painting | Interior paint labor | Blue Spruce Painting | $36,775 |
| 05/07/2026 | 220000 Plumbing systems | Rough-in plumbing draw | Clearwater Plumbing | $72,400 |
| 05/11/2026 | 220000 Plumbing systems | Fixture allowance purchase | PlumbLine Supply | $28,630 |
| 05/16/2026 | 230000 HVAC systems | Air handler equipment | NorthStar Mechanical | $64,900 |
| 05/20/2026 | 230000 HVAC systems | Ductwork install draw | NorthStar Mechanical | $91,250 |
| 05/25/2026 | 260000 Electrical systems | Electrical rough-in labor | VoltWorks Electric | $84,150 |
| 05/29/2026 | 260000 Electrical systems | Panel and switchgear package | Evergreen Electrical Supply | $53,680 |
| 06/04/2026 | 013100 Project management | Closeout documentation support | BuilderPad Internal | $6,950 |
| Totals | $1,300,525 | |||