Total Contract
$21,370,000
Active contract value
Earned revenue, billings, backlog, and over/under billing by active job
| Project | Contract | % Complete | Earned | Billed | Over/(Under) | Backlog |
|---|---|---|---|---|---|---|
| Ridgeview Custom Residence | $4,860,000 | 67% | $3,257,950 | $3,365,000 | $107,050 | $1,495,000 |
| Harbor Point Remodel | $2,240,000 | 58.3% | $1,305,562 | $1,210,000 | -$95,562 | $1,030,000 |
| Willow Creek Addition | $1,580,000 | 62.8% | $992,564 | $925,000 | -$67,564 | $655,000 |
| Cedar Lane Estate | $6,420,000 | 64.6% | $4,149,512 | $3,845,000 | -$304,512 | $2,575,000 |
| Juniper Flats Townhomes | $3,950,000 | 60.3% | $2,381,618 | $2,560,000 | $178,382 | $1,390,000 |
| Lakeside Guest House | $980,000 | 63.7% | $624,000 | $590,000 | -$34,000 | $390,000 |
| Oak Terrace Renovation | $1,340,000 | 80.4% | $1,077,307 | $1,010,000 | -$67,307 | $330,000 |
| Totals | $21,370,000 | 64.5% | $13,788,513 | $13,505,000 | -$283,513 | $7,865,000 |