Baseline-vs-actual schedule variance by project, phase, and the tasks slipping furthest
Average item variance, sorted by projects losing the most time
Cross-project averages by phase name
The tasks pulling the schedule furthest past baseline
| Item | Project | Phase | Planned end | Actual end | Variance |
|---|---|---|---|---|---|
| Mechanical Rough-In | Pine View Addition | Rough-Ins | Dec 30, 2025 | Jan 9, 2026 | +10d |
| Electrical Rough-In | Lakeside Custom Home | Rough-Ins | Apr 24, 2025 | May 2, 2025 | +8d |
| Electrical Rough-In | Oak Hollow Remodel | Rough-Ins | Oct 2, 2025 | Oct 10, 2025 | +8d |
| MEP Inspection | Pine View Addition | Rough-Ins | Jan 8, 2026 | Jan 16, 2026 | +8d |
| Certificate of Occupancy | Summit Ridge Residence | Closing | Sep 18, 2026 | Sep 25, 2026 | +7d |
| Client Handoff | Summit Ridge Residence | Closing | Sep 21, 2026 | Sep 28, 2026 | +7d |
| Warranty Orientation | Summit Ridge Residence | Closing | Sep 22, 2026 | Sep 29, 2026 | +7d |
| Plumbing Rough-In | Lakeside Custom Home | Rough-Ins | Apr 18, 2025 | Apr 25, 2025 | +7d |