Projects
5
With a baseline
Baseline-vs-actual schedule variance by project, phase, and the tasks slipping furthest
Average item variance, sorted by projects losing the most time
Cross-project averages by phase name
The tasks pulling the schedule furthest past baseline
| Item | Project | Phase | Planned end | Actual end | Variance |
|---|---|---|---|---|---|
| Mechanical Rough-In | Summit Office Buildout | Rough-Ins | Dec 30, 2025 | Jan 9, 2026 | +10d |
| Electrical Rough-In | Morrow Lake House | Rough-Ins | Apr 24, 2025 | May 2, 2025 | +8d |
| Electrical Rough-In | Elmwood Renovation | Rough-Ins | Oct 2, 2025 | Oct 10, 2025 | +8d |
| MEP Inspection | Summit Office Buildout | Rough-Ins | Jan 8, 2026 | Jan 16, 2026 | +8d |
| Plumbing Rough-In | Morrow Lake House | Rough-Ins | Apr 18, 2025 | Apr 25, 2025 | +7d |
| Plumbing Topout | Cypress Ridge Custom | Rough-Ins | Jul 4, 2025 | Jul 11, 2025 | +7d |
| Plumbing Rough-In | Elmwood Renovation | Rough-Ins | Oct 10, 2025 | Oct 17, 2025 | +7d |
| Low Voltage Rough-In | Summit Office Buildout | Rough-Ins | Dec 12, 2025 | Dec 19, 2025 | +7d |