Truss set — roof structure complete — Truss delivery was two hours late again; Ridgeline are on notice. Crew of six, 8.5 hrs. Check the north gable overhang against the plans.
Posted to feed3photos
5:00 AM
Tuesday, Aug 11
Submitted
Mark ThompsonMark ThompsonMark Thompson
Wall sheathing — north and east — Sheathing north and east. Short four sheets, chased the supplier.
Posted to feed1photo
5:00 AM
Monday, Aug 10
Submitted
Mark ThompsonMark ThompsonMark Thompson
Stair landing rework — Stair landing framing is out of square. It comes out and goes back in Monday. Do not raise this with the owner until we know who carries the cost.
Posted to feed2safety incidents1photo
5:00 AM
Sunday, Aug 9
Submitted
Mark ThompsonMark ThompsonMark Thompson
Excavation complete — Excavation done. Hit rock on the east side, extra machine time — this is going to be a change order and the owner will not like it.
Posted to feed3photos
5:00 AM
Tuesday, Jun 16
AI
Auto Draft: Site Updates
Generated from 2 photos90% confident
1photo
6:00 AM
Monday, Jun 15
Draft
Mark ThompsonMark ThompsonMark Thompson
Site Walkthrough — Completed morning site walkthrough. All sub trades are on schedule.