Vendor
Title
Scheduled
Change Orders
Revised
Invoiced
%
Remaining
Status
001GW ConcreteConcrete foundations$45,000+$3,750$48,750$24,50050.26%$24,250Active002Apex Framing LLCFraming labor + materials$80,000—$80,000$00.00%$80,000Active003Cedar Creek MillworkCustom cabinetry$32,000—$32,000$00.00%$32,000Out for signaturePO 001Keystone Building SupplyAppliance package$15,000—$15,000$00.00%$15,000Pending007Valley Plumbing Co.Plumbing rough-in$18,400—$18,400$00.00%$18,400ActivePO 041Lowe'sNot linkedAppliance and hardware allowance$18,500—$18,500$00.00%$18,500Active Totals excl. cancelled$208,900+$3,750$212,650$24,50011.52%$188,150