50510 ExcavationSite excavation and haul-offMarullo Construction09/01/25 - 09/30/2509/30/25$36,800.00Subtotals:0510 Excavation$36,800.00
60610 Deck ConcreteElevated deck concrete pourMarullo Construction09/01/25 - 09/30/2509/30/25$27,250.0070610 Deck ConcreteDeck formwork and pump time54 Crane Service LLC09/01/25 - 09/30/2509/30/25$14,600.00Subtotals:0610 Deck Concrete$41,850.00
80790 PlumbingRough plumbing allowanceMarullo Construction09/01/25 - 09/30/2509/30/25$11,625.00Subtotals:0790 Plumbing$11,625.00
90840 ElectricalMain electrical rough-inKirby Brothers Electric09/01/25 - 09/30/2509/26/25$19,840.25100840 ElectricalLow-voltage pathwaysOdle Electric09/01/25 - 09/30/2509/28/25$22,615.00Subtotals:0840 Electrical$42,455.25
111010 Wood FloorWhite oak flooring depositTelluride Woodworks09/01/25 - 09/30/2509/30/25$16,375.00Subtotals:1010 Wood Floor$16,375.00
121110 SecuritySecurity prewireOdle Electric09/01/25 - 09/30/2509/30/25$8,940.00Subtotals:1110 Security$8,940.00
139990 Contractor FeeContractor feeBuilderPad09/01/25 - 09/30/2509/30/25$12,850.00Subtotals:9990 Contractor Fee$12,850.00